Question(s) similar to the following:

If your expected value is 110 and the standard deviation is 12, which of the following is true?

Question 1: If your expected value is 110 and the standard deviation is 12, which of the following is true?

There is approximately a 99 percent chance of completing this activity between 86 and 134 days
There is approximately a 68 percent chance of completing this activity between 98 and 122 days
There is approximately a 95 percent chance of completing this activity between 98 and 122 days
There is approximately a 75 percent chance of completing this activity between 86 and 134 days

Similar Questions:

Question 2: If your expected value is 110 and the standard deviation is 12, which of the following is true?

There is approximately a 99 percent chance of completing this activity between 86 and 134 days
There is approximately a 68 percent chance of completing this activity between 98 and 122 days
There is approximately a 95 percent chance of completing this activity between 98 and 122 days
There is approximately a 75 percent chance of completing this activity between 86 and 134 days
Quizzes of CS615 - Software Project Management
Sponsored

Attach VULMS for better learning experience!
Attach VULMS Account

Our VULMS adds features of MDBs and lets your populate VU subjects automatically.

Tajweed Classes (Learn Quran with Tajweed)
Learn Holy Quran with Tajweed

Try our 3 days free demo now! Online online holy quran tajweed classes are useful to learn reading holy quran with tajweed.

Gegasoft POS/CRM Software
Gegasoft Point of Sale/Customer Relationship Managemnet Software

Gegasoft Point of Sale/Customer Relationship Management software is an accounting software to fulfill your business needs.

Sponsored

?