In a development project, if an activity (i, j) of duration three days finish earlier on the tenth day then which of the following will be its earler start day?

Question 1: In a development project, if an activity (i, j) of duration three days finish earlier on the tenth day then which of the following will be its earler start day?

Seventh day
Third day
First day
Fifth day

Similar Questions:

Question 2: In a development project, if an activity (i, j) of duration three days finish earlier on the tenth day then which of the following will be its earler start day?

Seventh day
Third day
First day
Fifth day
Quizzes of MTH601 - Operations Research
Sponsored

Attach VULMS for better learning experience!
Attach VULMS Account

Our VULMS adds features of MDBs and lets your populate VU subjects automatically.

Tajweed Classes (Learn Quran with Tajweed)
Learn Holy Quran with Tajweed

Try our 3 days free demo now! Online online holy quran tajweed classes are useful to learn reading holy quran with tajweed.

Gegasoft POS/CRM Software
Gegasoft Point of Sale/Customer Relationship Managemnet Software

Gegasoft Point of Sale/Customer Relationship Management software is an accounting software to fulfill your business needs.

Sponsored

?