Question 1: A set of nodes connected by lines which begin at the initial node of work and end at the terminal node is called __________.
Critical path
Path
Node
Network
Q2
Question 2: Which one of the following is not an operations research problem solving steps?
observation
definition of the problems
variable selections
model construction
Q3
Question 3: Which of the following difficulty may found while attempting an LP problem by M-method?
It often loads to infeasible solution
Computational error due to large value of M
Degeneracy is inevitable
Artificial do not leave the basis
Q4
Question 4: In a development project, if an activity (i, j) of duration three days finish earlier on the tenth day then which of the following will be its earler start day?
Seventh day
Third day
First day
Fifth day
Q5
Question 5: Shortcoming of Big M method is that the value of M could be __________.
very small
very large
negative
positive
Q6
Question 6: In the phase of Early Start and Early Finish, to find the Critical Path in a network flow diagram, for the first node (event), we start with time __________.
t = infinity
t = 0
t = a (arbitrary)
with strict positive value
Q7
Question 7: In Project Management, Program Evaluation and Review Technique (PERT) is based on __________ times.
deterministic
probabilistic
stochastic
Serial
Q8
Question 8: There are __________ kinds of time calculations for a project.
Q9
Question 9: By Simplex method, to maximize \(Z = 2x + 9y\) an LP problem, if 'z=0' for the initial iteration then for its next improved solution, which of the following would be the next entering variable?
Q10
Question 10: Choose the correct one for the project times that are used in project management.
Latest start time, Latest finish time, Earliest start time, Earliest finish time
Latest start time, Latest finish time, Earliest start time, CPM
Latest start time, Latest finish time, PERT, Earliest finish time
PERT, CPM